Milis Flatwork collaborated closely with the owners to develop a detailed plan for this project, ensuring there were no disruptions to the storefront or business operations.
The team carefully scheduled pour times around the final delivery, with a strategic Friday pour using a 9-bag mix for the delivery drive lane.
This allowed for curing over the weekend, giving customers a place to park while the work was being completed. Through continuous communication among all parties, the process proceeded smoothly.
In total, the 21,000 square-foot concrete overlay was finished in three pours, utilizing 500 yards of unreinforced concrete.
The lot features 7 inches of concrete in the trucking area and 4 inches of concrete in the main parking section. The project was completed in September 2024.
Project Team Members
Owner: Lamers Dairy
Concrete Supplier: MCC, Inc.
Contractor/Engineer: Milis Flatwork